555 Broderick St #0
San Francisco permit 202606082737 · Hayes Valley
2 new adus on 1st floor per state adu program, ordinance no.95-17, new fire sprinkler system to be installed throughout the entire 1st floor in compliance with 2025 nfpa13 and eg-05, new heat pump water heaters and heating systems for each adu. a manual fire alarm system in compliance w/2025 nfpa72
- Filed
- Aug 20, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 33 stops across 7 departments
- Comments issued
- 8 times, by Permit Center, Planning, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 5, 2026 | Jun 23, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jun 24, 2026 | Jul 10, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Aug 4, 2026 | Aug 18, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 20, 2026 | Aug 20, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Aug 20, 2026 | Sep 4, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 20, 2026 | Aug 24, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 20, 2026 | Sep 9, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 20, 2026 | Sep 1, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 20, 2026 | Sep 9, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 20, 2026 | Aug 26, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 20, 2026 | Sep 8, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 20, 2026 | Sep 3, 2026 | Approved |
Public Health HEALTH-MH | Aug 20, 2026 | Aug 21, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 20, 2026 | In progress | — |
Zoning review Planning · CP-ZOC | Sep 21, 2026 | Oct 21, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 21, 2026 | Sep 24, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 21, 2026 | Sep 29, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 21, 2026 | Sep 30, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 21, 2026 | Sep 22, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 21, 2026 | Sep 23, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 21, 2026 | Sep 22, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 21, 2026 | Sep 24, 2026 | Approved |
Public Health HEALTH-MH | Sep 21, 2026 | Sep 21, 2026 | Not Applicable |
Zoning review Planning · CP-ZOC | Oct 22, 2026 | Oct 30, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 22, 2026 | Oct 30, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 22, 2026 | Nov 2, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 22, 2026 | Oct 27, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Oct 22, 2026 | Oct 23, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 22, 2026 | Oct 26, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 22, 2026 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 22, 2026 | Oct 23, 2026 | Approved |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $330,815
| Name | Role | License on permit |
|---|---|---|
| Stacy Chien-Yu Lin Arkichik | Architect | C30812 |
| Donald David Double D Engineering | Engineer | S3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2025