34 St Marys Av
San Francisco permit 202606092882 · Bernal Heights
First floor horizozntal addition (increase of 131sq ft of habitable living space). second floor vertical addition (increase of 681 sq ft of habitable living space). rear patio replacement. interior remodel.
- Filed
- Aug 6, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 16 stops across 6 departments
- Comments issued
- 4 times, by Permit Center, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 5, 2026 | Jun 25, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jun 29, 2026 | Jul 10, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 10, 2026 | Aug 10, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Aug 10, 2026 | Oct 15, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 10, 2026 | Oct 21, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 10, 2026 | Oct 19, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Aug 10, 2026 | Sep 1, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 10, 2026 | Aug 21, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 10, 2026 | Aug 11, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 10, 2026 | Sep 9, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 10, 2026 | Aug 24, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 10, 2026 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Aug 27, 2026 | Aug 27, 2026 | Approved |
Building plan review Building Inspection · BLDG | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $480,000
| Name | Role | License on permit |
|---|---|---|
| Antje Paiz Raumfabrik Architecture | Architect | C31989 |
| Peter David Bonneau Peter Bonneau Struc Design Inc | Engineer | 81545 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026