As written on the permit application.

Erect a 3 story and one dwelling single family dwelling with adu,no basement. type v-b

Timeline
Key dates from the city record.
Filed
Oct 7, 2026
Issued
Not issued yet
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
18 stops across 6 departments
Comments issued
3 times, by Permit Center, Building Inspection, Public Utilities
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jun 24, 2026Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Aug 24, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Oct 8, 2026Administrative

Zoning review

Planning · CP-ZOC

Oct 14, 2026Approved

Building plan review

Building Inspection · BLDG

In progress—

Structural plan approval

Building Inspection · PAD-STR

In progress—

Mechanical and energy plan review

Building Inspection · MECH

Oct 22, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Oct 21, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Oct 8, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Oct 8, 2026Approved

Urban forestry

Public Works · DPW-BUF

In progress—

Public Utilities Commission review

Public Utilities · SFPUC

Oct 26, 2026Issued Comments

Public Utilities programs review

Public Utilities · SFPUC-PRG

Oct 30, 2026Approved

Permit Processing Center

Building Inspection · PPC

In progress—

Public Utilities Commission review

Public Utilities · SFPUC

Oct 30, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

In progress—

Development fee collection

Building Inspection · DFCU

In progress—

Central Permit Bureau

Building Inspection · CPB

In progress—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction wood frame
Status
Filed
Estimated cost
$905,500
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Geoffrey Gibson

Winder Gison Architects

ArchitectC35924
Erevan O'neill

One Design

EngineerC75459
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202606112981 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record