2061 Mission St
San Francisco permit 202606163356 · Mission
Priority:13-01: legalize unit 35 through the state adu round table process. reconfiguration of units 19,33 & 34
- Filed
- Aug 9, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 21 stops across 6 departments
- Comments issued
- 6 times, by Permit Center, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 13, 2026 | Jul 2, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jul 16, 2026 | Aug 5, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 6, 2026 | Aug 10, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Aug 10, 2026 | Aug 11, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 10, 2026 | Sep 14, 2026 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Aug 10, 2026 | Sep 11, 2026 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Aug 10, 2026 | Sep 15, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 10, 2026 | Aug 31, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 10, 2026 | Aug 13, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 10, 2026 | Aug 11, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 10, 2026 | Sep 24, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 10, 2026 | Sep 4, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 10, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Building plan review quality control Building Inspection · BLDG-QC | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Paul Alahin Molina Molina & Timmins Architect | Authorized agent-others | C30600 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026