4 Embarcadero Center
San Francisco permit 202606183547 · Financial District/South Beach
39th & 40th flrs: tenant improvement including: * selective demolition of offices and pantry * new non-load bearing partitions, ceiling, light fixtures & finishes * new operable partitions
- Filed
- Jul 22, 2026
- Issued
- Oct 19, 2026 (3 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 15 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 16, 2026 | Jul 7, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 8, 2026 | Jul 22, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jul 22, 2026 | Aug 14, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 22, 2026 | Aug 17, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jul 22, 2026 | Aug 6, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 22, 2026 | Aug 31, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 22, 2026 | Aug 17, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 22, 2026 | Oct 5, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Sep 14, 2026 | Sep 25, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 14, 2026 | Sep 24, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 22, 2026 | Sep 23, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 25, 2026 | Sep 29, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 28, 2026 | Oct 1, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 2, 2026 | Oct 2, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 5, 2026 | Oct 19, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $4,556,700
| Name | Role | License on permit |
|---|---|---|
| Luda Hoe Gensler | Architect | C38081 |
| Leo Panian | Engineer | S4526 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2017