233 Douglass St
San Francisco permit 202606223678 · Castro/Upper Market
To create a new junior adu in the existing ground floor (using the state program).
- Filed
- Aug 17, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 21 stops across 6 departments
- Comments issued
- 4 times, by Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 17, 2026 | Jul 8, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 8, 2026 | Aug 18, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Aug 18, 2026 | Aug 24, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 18, 2026 | Aug 20, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 18, 2026 | Aug 24, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 18, 2026 | Aug 20, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 18, 2026 | Aug 19, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 18, 2026 | Sep 1, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 18, 2026 | Aug 31, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Aug 18, 2026 | Sep 23, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 3, 2026 | Sep 16, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 3, 2026 | Sep 14, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 3, 2026 | Sep 14, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 3, 2026 | Sep 8, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Sep 3, 2026 | Sep 9, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 3, 2026 | Sep 22, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 3, 2026 | Sep 15, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 8, 2026 | Sep 9, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Sep 22, 2026 | Sep 23, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 23, 2026 | In progress | In Progress |
Address verification Building Inspection · ADDR | Sep 30, 2026 | Sep 30, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Approved
- Estimated cost
- $112,723
| Name | Role | License on permit |
|---|---|---|
| Marc A Lindsell 2m Architecture | Architect | C25915 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023