571 Eureka St
San Francisco permit 202606263972 · Noe Valley
Add ground floor unit via state adu program per planning code section 207.2. replace 4 windows at rear and light well walls.
- Filed
- Jul 7, 2026
- Issued
- Sep 16, 2026 (2 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 21 stops across 6 departments
- Comments issued
- 4 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 22, 2026 | Jul 6, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 7, 2026 | Jul 7, 2026 | Administrative |
Permit Processing Center Building Inspection · PPC | Jul 7, 2026 | Sep 16, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jul 8, 2026 | Jul 14, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 8, 2026 | Jul 14, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 8, 2026 | Jul 17, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 8, 2026 | Jul 10, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 8, 2026 | Jul 13, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 8, 2026 | Aug 3, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 8, 2026 | Jul 27, 2026 | Approved |
Zoning review Planning · CP-ZOC | Aug 20, 2026 | Sep 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 20, 2026 | Aug 24, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 20, 2026 | Aug 28, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 20, 2026 | Aug 24, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Aug 20, 2026 | Aug 26, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 20, 2026 | Sep 8, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 20, 2026 | Aug 31, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 24, 2026 | Aug 26, 2026 | Approved-Stipulated |
Development fee collection Building Inspection · DFCU | Sep 8, 2026 | Sep 8, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 8, 2026 | Sep 16, 2026 | Administrative |
Address verification Building Inspection · ADDR | Sep 14, 2026 | Sep 14, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $158,563
| Name | Role | License on permit |
|---|---|---|
| My My Ly Mml Architect | Architect | C-32972 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025