4145 Ocean Av
San Francisco permit 202606263986 · Sunset/Parkside
Convert two car attached garage into conditioned space in lower level of a 2 story split level sfd. remodel lower level to include a new kitchen, bedroom, bath & laundry.upper floor work entails only straightening stair down to lower level. laundry moved from mechanical basement to new laundry room.
- Filed
- Jul 14, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 37 stops across 6 departments
- Comments issued
- 9 times, by Planning, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 24, 2026 | Jul 13, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 26, 2026 | Jul 14, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jul 15, 2026 | Jul 17, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 15, 2026 | Jul 20, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 15, 2026 | Jul 28, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 15, 2026 | Jul 22, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 15, 2026 | Jul 16, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jul 15, 2026 | Jul 16, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jul 15, 2026 | Jul 27, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 15, 2026 | Jul 20, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 15, 2026 | Oct 22, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Aug 26, 2026 | Sep 16, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 26, 2026 | Sep 2, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 26, 2026 | Sep 16, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 26, 2026 | Sep 2, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 26, 2026 | Sep 3, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Aug 26, 2026 | Aug 31, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Aug 26, 2026 | Sep 15, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 26, 2026 | Sep 3, 2026 | Approved |
Zoning review Planning · CP-ZOC | Sep 18, 2026 | Sep 21, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 18, 2026 | Sep 24, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 18, 2026 | Oct 1, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 18, 2026 | Sep 25, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 18, 2026 | Sep 20, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Sep 18, 2026 | Sep 23, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 18, 2026 | Sep 22, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 18, 2026 | Sep 22, 2026 | Approved |
Zoning review Planning · CP-ZOC | Oct 2, 2026 | Oct 5, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 2, 2026 | Oct 13, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 2, 2026 | Oct 2, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 2, 2026 | Oct 6, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Oct 2, 2026 | Oct 5, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Oct 2, 2026 | Oct 6, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 2, 2026 | Oct 21, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 2, 2026 | Oct 6, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Oct 21, 2026 | Oct 21, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 22, 2026 | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $195,949
| Name | Role | License on permit |
|---|---|---|
| Ryan G Morris Morris Architecture | Architect | C33359 |
| Robert Hugh Shaffer Morris Shaffer Engineering | Engineer | C45322 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2025