64 Woodland Av #0
San Francisco permit 202606304283 · Inner Sunset
legalize existing ground-floor finished space as a state adu under san francisco planning code section 207.2. work required for adu code compliance is limited to items shown in the drawings and related compliance documents, including field verification and documentation of existing floor/ ceiling
- Filed
- Aug 28, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 18 stops across 6 departments
- Comments issued
- 6 times, by Permit Center, Planning, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 30, 2026 | Jul 23, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Aug 8, 2026 | Aug 24, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 31, 2026 | Aug 31, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Aug 31, 2026 | Sep 16, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 31, 2026 | Sep 8, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 31, 2026 | Sep 15, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 31, 2026 | Sep 4, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 31, 2026 | Sep 3, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 31, 2026 | Sep 23, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 31, 2026 | Sep 16, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 31, 2026 | In progress | — |
Zoning review Planning · CP-ZOC | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $1,000
| Name | Role | License on permit |
|---|---|---|
| Howard E Blecher Blecher Bldg & Urban Design | Architect | C-36464 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025