2245 Union St
San Francisco permit 202606304286 · Marina
Work includes a small rear horizontal addition at the existing 1st and 2nd flrs, a new basement level below the house. for a garage and storage spaces, and an interior remodel of other existing spaces of the home. exterior improvements include new garage door, reframe existing front walk-up stairs.
- Filed
- Jun 30, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 21 stops across 7 departments
- Comments issued
- 5 times, by Permit Center, Planning, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 30, 2026 | Jul 17, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jul 21, 2026 | Aug 7, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 10, 2026 | Aug 12, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Aug 12, 2026 | Sep 2, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 12, 2026 | Oct 23, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Aug 12, 2026 | In progress | In Progress |
Structural plan approval Building Inspection · PAD-STR | Aug 12, 2026 | Oct 22, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 12, 2026 | In progress | In Progress |
Fire prevention review Fire Department · SFFD | Aug 12, 2026 | Aug 25, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 12, 2026 | Aug 20, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 12, 2026 | Aug 19, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 12, 2026 | Aug 24, 2026 | Approved |
Public Health HEALTH-MH | Aug 12, 2026 | Aug 25, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 12, 2026 | In progress | — |
Building plan review quality control Building Inspection · BLDG-QC | Oct 19, 2026 | Oct 23, 2026 | Not Applicable |
Zoning review Planning · CP-ZOC | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $990,000
| Name | Role | License on permit |
|---|---|---|
| Brian T Milford Martinkovie Milford Arch | Architect | C33430 |
| Shaun Edward Moynahan Semco Engineering | Engineer | S4605 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2016