25 Chattanooga St
San Francisco permit 202606304373 · Noe Valley
Conversion of an (e) basement storage & crawlspace into an attached adu.the adu project generally consists of a (n) open living/dining/kitchen,(n) bedroom,(n) office, (n) bath. ground floor rear addition w/deck above.
- Filed
- Aug 13, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 27 stops across 6 departments
- Comments issued
- 9 times, by Permit Center, Planning, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 30, 2026 | Jul 21, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jul 22, 2026 | Aug 12, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 13, 2026 | Aug 14, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Aug 14, 2026 | Sep 21, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 14, 2026 | Sep 11, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 14, 2026 | Sep 11, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 14, 2026 | Aug 31, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Aug 14, 2026 | Aug 14, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 14, 2026 | Aug 17, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 14, 2026 | Sep 16, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 14, 2026 | Aug 31, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 14, 2026 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 10, 2026 | Sep 21, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Sep 10, 2026 | Sep 11, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Sep 10, 2026 | Sep 14, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 10, 2026 | Sep 14, 2026 | Approved |
Zoning review Planning · CP-ZOC | Oct 22, 2026 | Nov 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 22, 2026 | Oct 23, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 22, 2026 | Oct 23, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 22, 2026 | Oct 27, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Oct 22, 2026 | Oct 23, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Oct 22, 2026 | Oct 22, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 22, 2026 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 22, 2026 | Oct 22, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $280,000
| Name | Role | License on permit |
|---|---|---|
| Renato M Jose Renato Jose I Architect | Architect | C28111 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026