1306 York St
San Francisco permit 202607024479 · Mission
Mep includes (n) heat pump, lighting, electrical, electrical, plumbing. install wsher dryer hookup on 3rd fl, new bathroom on 3rd floor. raise primary 3rd floor bedroom ceiling from 8'4"-9'. new skylights
- Filed
- Jul 2, 2026
- Issued
- Aug 21, 2026 (2 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2026 were typically issued within 1 month (median of 3,682 issued permits).
- Review stops
- 9 stops across 4 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jul 2, 2026 | Jul 2, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jul 2, 2026 | Jul 2, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 10, 2026 | Jul 10, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jul 10, 2026 | Jul 10, 2026 | Not Applicable |
Building plan review Building Inspection · BLDG | Aug 3, 2026 | Aug 3, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 4, 2026 | Aug 4, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 5, 2026 | Aug 5, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 6, 2026 | Aug 6, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 21, 2026 | Aug 21, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $195,000
| Name | Role | License on permit |
|---|---|---|
| Shaun Edward Moynahan Semco Engineering | Engineer | S4605 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026