222 28th Av
San Francisco permit 202607064586 · Seacliff
Excavation and remodel to 1st floor garage level to provide a bedroom, bath and laundry, family room, and garage. remodel (e) kitchen, relocate powder, and relocate stairs to 1st floor on 2nd level. relocate doors at (e) bath and (e) closets on the 3rd floor. replace (e) furnace with ductless mini
- Filed
- Jul 6, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 12 stops across 5 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 2, 2026 | Jul 23, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 24, 2026 | Jul 27, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jul 27, 2026 | Aug 13, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 27, 2026 | Oct 15, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 27, 2026 | Oct 15, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Jul 27, 2026 | Aug 20, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 27, 2026 | Aug 20, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 27, 2026 | Aug 14, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 27, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $1,000,000
| Name | Role | License on permit |
|---|---|---|
| Kim Trang Ngo Ngo Studio | Architect | C35713 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026