68 Blake St
San Francisco permit 202607144967 · Presidio Heights
Single story rear yard addittion, new roof extenstion to match existing roof. dig out lower basement under the proposed new addition. interior remodel, revise rear patio at grade.project is subject to ab112 all-electric ordinance.
- Filed
- Sep 10, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 16 stops across 6 departments
- Comments issued
- 4 times, by Permit Center, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 13, 2026 | Jul 30, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Aug 19, 2026 | Sep 9, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 10, 2026 | Sep 10, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 10, 2026 | Oct 26, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 10, 2026 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Sep 10, 2026 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 10, 2026 | Oct 6, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 10, 2026 | Sep 21, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 10, 2026 | Sep 15, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 10, 2026 | Oct 9, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 10, 2026 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Electrical plan review Building Inspection · MECH-E | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Mia K Zinni Mza Ltd. | Architect | C39469 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025