1 Market St
San Francisco permit 202607155063 · Financial District/South Beach
1st fl: interior oly tenant improvement to construct new fitness center. mep deferred.
- Filed
- Jul 15, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 9 stops across 4 departments
- Comments issued
- Once, by Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jul 15, 2026 | Jul 15, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jul 15, 2026 | Jul 15, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 13, 2026 | Aug 13, 2026 | Not Applicable |
Building plan review Building Inspection · BLDG | Oct 2, 2026 | Oct 2, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 5, 2026 | Oct 5, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 5, 2026 | Oct 5, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 5, 2026 | Oct 5, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Oct 7, 2026 | Oct 7, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Filed
- Estimated cost
- $3,115,000
| Name | Role | License on permit |
|---|---|---|
| Stephanie Kwan | Architect | C37048 |
| Edward Rivera Rivera Consulting Group Inc | Engineer | 2835 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026