83 Harrington St
San Francisco permit 202607175169 · Outer Mission
Raise existing single family dwelling +-24". expand 3rd floor with gable roof, remodel interior with new stairs. subject to ab-112, all electric ordinance.
- Filed
- Aug 23, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 22 stops across 6 departments
- Comments issued
- 9 times, by Permit Center, Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 12, 2026 | Jul 31, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Aug 3, 2026 | Aug 19, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 21, 2026 | Aug 24, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Aug 24, 2026 | Sep 8, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 24, 2026 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Aug 24, 2026 | Nov 2, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 24, 2026 | Sep 23, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 24, 2026 | Sep 10, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 24, 2026 | Aug 27, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 24, 2026 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 24, 2026 | Sep 8, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Aug 24, 2026 | In progress | — |
Electrical plan review Building Inspection · MECH-E | Sep 23, 2026 | Sep 29, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 2, 2026 | Oct 2, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 13, 2026 | Oct 15, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 26, 2026 | Nov 3, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Electrical plan review Building Inspection · MECH-E | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $380,000
| Name | Role | License on permit |
|---|---|---|
| Jeremiah W P Schaub Schaub | Li | Architects | Architect | C-32289 |
| Man Yip Li Schaub Ly Architects | Architect | — |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022