1215 Bay St
San Francisco permit 202607215310 · Marina
Alteration of the space of one (e) parking space, storage room & partial laundry room for a new adu within (e) building envelope.
- Filed
- Sep 21, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 19 stops across 6 departments
- Comments issued
- 6 times, by Permit Center, Planning, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 15, 2026 | Aug 3, 2026 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Jul 21, 2026 | Sep 21, 2026 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Sep 9, 2026 | Sep 17, 2026 | Approved |
Zoning review Planning · CP-ZOC | Sep 21, 2026 | Oct 16, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 21, 2026 | Oct 5, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 21, 2026 | Oct 13, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 21, 2026 | Oct 7, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 21, 2026 | Sep 24, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 21, 2026 | Sep 22, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 21, 2026 | Oct 20, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 21, 2026 | Oct 13, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 21, 2026 | In progress | — |
Zoning review Planning · CP-ZOC | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $70,000
| Name | Role | License on permit |
|---|---|---|
| Edward Davis Morris Kerman Morris Architects Llp | Architect | C24585 |
| Engin Yagmur Ecr Engineering | Engineer | 76016 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023