Covert (e) detached garage into adu. work to be performed within (e) walls, change roof structure from flat to shed within (e) envelop. no addition or extension. project will comply with all-electric per the sfdbi ab-112.

Timeline
Key dates from the city record.
Filed
Oct 4, 2026
Issued
Not issued yet
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
20 stops across 6 departments
Comments issued
5 times, by Permit Center, Planning, Building Inspection
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Aug 10, 2026Issued Comments

Central Permit Bureau

Building Inspection · CPB

Oct 5, 2026Administrative

Permit Center

Permit Center · PERMIT-CTR

Sep 4, 2026Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Sep 23, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Oct 5, 2026Administrative

Address verification

Building Inspection · ADDR

In progress—

Zoning review

Planning · CP-ZOC

Oct 16, 2026Issued Comments

Building plan review

Building Inspection · BLDG

Oct 14, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

In progress—

Mechanical and energy plan review

Building Inspection · MECH

Oct 23, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Oct 8, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Oct 6, 2026Approved

Urban forestry

Public Works · DPW-BUF

In progress—

Public Utilities Commission review

Public Utilities · SFPUC

Oct 23, 2026Approved

Permit Processing Center

Building Inspection · PPC

In progress—

Zoning review

Planning · CP-ZOC

In progress—

Building plan review

Building Inspection · BLDG

In progress—

Mechanical and energy plan review

Building Inspection · MECH

In progress—

Development fee collection

Building Inspection · DFCU

In progress—

Central Permit Bureau

Building Inspection · CPB

In progress—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Filed
Estimated cost
$500,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Lawrence Tik Man Wong

L Wong Engineering

Engineer5135
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202607235434 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record