1725 03rd St
San Francisco permit 202608056076 · Mission Bay
Partial floor tenant improvement of the 3rd floor.
- Filed
- Aug 5, 2026
- Issued
- Sep 10, 2026 (1 month after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2026 were typically issued within 1 month (median of 3,682 issued permits).
- Review stops
- 12 stops across 4 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 5, 2026 | Aug 5, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Aug 5, 2026 | Aug 5, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 5, 2026 | Aug 5, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 13, 2026 | Aug 13, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 13, 2026 | Aug 13, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Aug 13, 2026 | Aug 13, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 13, 2026 | Aug 13, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 17, 2026 | Aug 17, 2026 | Approved |
Permit Center Permit Center · PERMIT-CTR | Aug 17, 2026 | Aug 17, 2026 | — |
Redevelopment review Redevelopment · REDEV | Aug 17, 2026 | Sep 1, 2026 | Approved |
Permit Center Permit Center · PERMIT-CTR | Sep 2, 2026 | Sep 2, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 10, 2026 | Sep 10, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $847,444
| Name | Role | License on permit |
|---|---|---|
| Adam Zdzislaw Murphy | Architect | C-29238 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026