1921 Ellis St
San Francisco permit 202608066161 · Western Addition
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa #202508263944 3rd floor unit #1921 to reconfigure master bathroom, relocate non load-bearing walls, add skylight in kitchen, seal one existing window, revise lighting layout; revise all proposed door height to 96"
- Filed
- Aug 6, 2026
- Issued
- Aug 21, 2026 (within 1 month of filing)
- Completed
- Not completed yet
- Review stops
- 5 stops across 2 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 6, 2026 | Aug 6, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Aug 6, 2026 | Aug 6, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 6, 2026 | Aug 6, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 6, 2026 | Aug 6, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 21, 2026 | Aug 21, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Jeff Chow Aavenyr | Architect | C81252 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025