141 Leland Av
San Francisco permit 202608106348 · Visitacion Valley
Remove (e) fence, pedestrian gate, vehicular gate, parking lighting. and provide new fence, pedestrian gate, vehicular gate, in place of (e), provide new post mounted, parking lighting, paving for pot and parking, underground infraestructure for future ev charger.
- Filed
- Aug 10, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 11 stops across 4 departments
- Comments issued
- Twice, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 10, 2026 | Aug 10, 2026 | Administrative |
Apartment and hotel inspection Building Inspection · HIS | Aug 10, 2026 | Aug 10, 2026 | Approved |
Zoning review Planning · CP-ZOC | Aug 10, 2026 | Aug 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 10, 2026 | Aug 10, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 20, 2026 | Aug 20, 2026 | Not Applicable |
Electrical plan review Building Inspection · MECH-E | Aug 20, 2026 | Aug 20, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 15, 2026 | Sep 15, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 15, 2026 | Sep 15, 2026 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Sep 15, 2026 | Sep 15, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Filed
- Estimated cost
- $35,000
| Name | Role | License on permit |
|---|---|---|
| Austen Boyd Diliberto Studio Nea | Architect | C36278 |
| Jacqueline Lingwei Luk Luk And Associates | Engineer | C75724 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026