125 03rd St #0
San Francisco permit 202608116405 · Financial District/South Beach
Construct permanent tent on 4/f to be fire sprinkled and alarmed. new lighting and receptacles for temp event lighting. no change to (e) roof drainage.
- Filed
- Oct 6, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 13 stops across 4 departments
- Comments issued
- 3 times, by Permit Center, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 10, 2026 | Aug 26, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Aug 26, 2026 | Sep 11, 2026 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Oct 6, 2026 | Oct 6, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Oct 6, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | Oct 6, 2026 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Oct 6, 2026 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 6, 2026 | Nov 4, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 6, 2026 | Oct 14, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 6, 2026 | In progress | — |
Permit Processing Center Building Inspection · PPC | Oct 6, 2026 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Electrical plan review Building Inspection · MECH-E | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $4,217,680
| Name | Role | License on permit |
|---|---|---|
| Mark Robert Cavagnero Mark Cavagnero Associates | Architect | C-19521 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026