250 El Camino Del Mar
San Francisco permit 202608186750 · Seacliff
Mod & replace ext finishes - replace windows and skylight. infill at 2 terraces on 3/f. n/s 2/f - infill patio under overhang. mod front bay. at roof terrace provide (n) w/p membrane, new ceramic paves on pedestals,(n) railings. add sauna & laundry. ab-112
- Filed
- Sep 4, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 16 stops across 6 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 17, 2026 | Sep 3, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 4, 2026 | Sep 4, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 4, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | Sep 4, 2026 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Sep 4, 2026 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 4, 2026 | Oct 8, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 4, 2026 | Sep 9, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 4, 2026 | Sep 15, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 4, 2026 | Sep 25, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 4, 2026 | In progress | — |
Fire prevention review Fire Department · SFFD | Sep 11, 2026 | Sep 11, 2026 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Oct 7, 2026 | Oct 7, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 8, 2026 | Oct 19, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Electrical plan review Building Inspection · MECH-E | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $790,000
| Name | Role | License on permit |
|---|---|---|
| Troy A Kashanipour Troy Kashanipour | Architect | C27646 |
| Javed Jaffarali Tharani Nabi Const & Engineering | Engineer | C-57676 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023