18 Tiffany Av
San Francisco permit 202608206920 · Bernal Heights
Alteration of 2 units comprising of 4 bedrooms and 2 baths, kitchen and new stairs will be repaced. add foundation and retmain wall in back yard. reconfig 1/f unit, remodel 2/f.
- Filed
- Aug 20, 2026
- Issued
- Oct 13, 2026 (2 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2026 were typically issued within 1 month (median of 3,682 issued permits).
- Review stops
- 12 stops across 4 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 20, 2026 | Aug 20, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Aug 20, 2026 | Aug 20, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 20, 2026 | Aug 20, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 20, 2026 | Aug 20, 2026 | Issued Comments |
Intake Building Inspection · INTAKE | Sep 30, 2026 | Sep 30, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 30, 2026 | Sep 30, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 13, 2026 | Oct 13, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 13, 2026 | Oct 13, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 13, 2026 | Oct 13, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Oct 13, 2026 | Oct 13, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 13, 2026 | Oct 13, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 13, 2026 | Oct 13, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $720,000
| Name | Role | License on permit |
|---|---|---|
| Jesse Reonardy | Engineer | C91196 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026