1038 Capitol Av
San Francisco permit 202608216983 · Oceanview/Merced/Ingleside
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa # 202607165151 - remove bathroom on ground floor from existing plan and remove bearing wall.
- Filed
- Aug 21, 2026
- Issued
- Aug 21, 2026 (within 1 month of filing)
- Completed
- Not completed yet
- Review stops
- 8 stops across 4 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 21, 2026 | Aug 21, 2026 | Administrative |
Building inspector Building Inspection · BID-INSP | Aug 21, 2026 | Aug 21, 2026 | Approved |
Zoning review Planning · CP-ZOC | Aug 21, 2026 | Aug 21, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 21, 2026 | Aug 21, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 21, 2026 | Aug 21, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 21, 2026 | Aug 21, 2026 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Aug 21, 2026 | Aug 21, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 21, 2026 | Aug 21, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Victor Ramos Ashley & Vance Engineering | Engineer | C86568 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025