2853 Green St
San Francisco permit 202608287334 · Pacific Heights
New construction of a 2-story type v-b adu in rear lot to include a gym with crawlspace, studio space with a kitchen, bathroom and sauna.
- Filed
- Sep 22, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 22 stops across 6 departments
- Comments issued
- 7 times, by Planning, Building Inspection, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 26, 2026 | Sep 16, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 22, 2026 | Sep 22, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 22, 2026 | Oct 27, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 22, 2026 | Oct 7, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 22, 2026 | Oct 21, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 22, 2026 | Oct 19, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 22, 2026 | Sep 25, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 22, 2026 | Sep 22, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 22, 2026 | Oct 27, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 22, 2026 | Oct 9, 2026 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Sep 22, 2026 | Oct 9, 2026 | Approved |
Address verification Building Inspection · ADDR | Sep 22, 2026 | In progress | — |
Permit Processing Center Building Inspection · PPC | Sep 22, 2026 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 22, 2026 | Oct 22, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 27, 2026 | Oct 27, 2026 | Approved |
Zoning review Planning · CP-ZOC | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Filed
- Estimated cost
- $145,000
| Name | Role | License on permit |
|---|---|---|
| Nate Williams Mosswood Engineering | Engineer | C62068 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2008