731 Columbus Av
San Francisco permit 202609027604 · Chinatown
1/f t.i. w/ added drink service and ext mods. int:(n) mercantile and espresso bar layout, new pvt loung space; ada upgrades. add ada restroom; new moment frames. ext: new finishes & tile, add canopy at entry, new exterior signage (sep); shift entry doors/config.
- Filed
- Sep 23, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 17 stops across 6 departments
- Comments issued
- 4 times, by Planning, Building Inspection, Public Utilities, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 1, 2026 | Sep 22, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 23, 2026 | Sep 23, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 24, 2026 | Oct 5, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 24, 2026 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Sep 24, 2026 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 24, 2026 | In progress | In Progress |
Electrical plan review Building Inspection · MECH-E | Sep 24, 2026 | Oct 8, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 24, 2026 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 24, 2026 | Oct 20, 2026 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Sep 24, 2026 | Oct 16, 2026 | Approved |
Public health food review Public Health · HEALTH-FD | Sep 24, 2026 | Oct 13, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Sep 24, 2026 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 22, 2026 | Oct 22, 2026 | Approved |
Zoning review Planning · CP-ZOC | — | In progress | — |
Electrical plan review Building Inspection · MECH-E | — | In progress | — |
Public health food review Public Health · HEALTH-FD | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $1,942,026
| Name | Role | License on permit |
|---|---|---|
| Hans Rainer Baldauf Bcv Architects | Architect | C22624 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026