279 Diamond St
San Francisco permit 202609037682 · Castro/Upper Market
Horizontal addition at rear 1st floor and 2nd floor, new roof deck over 1st floor, new stairs to rear yard.
- Filed
- Sep 18, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 14 stops across 6 departments
- Comments issued
- Twice, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 28, 2026 | Sep 11, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 17, 2026 | Sep 18, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 18, 2026 | Oct 1, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 18, 2026 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Sep 18, 2026 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 18, 2026 | Oct 28, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 18, 2026 | Sep 25, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Sep 18, 2026 | Sep 23, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 18, 2026 | Oct 7, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 18, 2026 | In progress | — |
Fire prevention review Fire Department · SFFD | Sep 25, 2026 | Oct 14, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $100,000
| Name | Role | License on permit |
|---|---|---|
| Brooks Mitchell Mcdonald Brooks Mcdonald Architecture | Architect | C33087 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022