809 Montgomery St
San Francisco permit 202609097818 · Chinatown
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Deferred metal stair permit associated with pa# 202607155078,shop drawings for exterior structural steel staircase (stair 4&5) stairs 4/5 runs from the finished grade to level 1, level 2b, and level 3 of 809 montgomery
- Filed
- Sep 22, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 8 stops across 4 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 3, 2026 | Sep 18, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 21, 2026 | Sep 22, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 22, 2026 | Sep 24, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 22, 2026 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Sep 22, 2026 | In progress | — |
Fire prevention review Fire Department · SFFD | Sep 22, 2026 | Oct 23, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 22, 2026 | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Nuno Machado Lopes | Architect | C31066 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022