679 03rd St
San Francisco permit 202609168210 · Financial District/South Beach
3/f - interior remodel. reconfigure (e) interior spaces w/ one conferecne room, one storage, two ada restrooms, open office area, one kitchentte. remove & relocate non load bearing walls. remove (e) sink and unused shower. install sink water closet for new ada restrooms.
- Filed
- Sep 16, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 14 stops across 4 departments
- Comments issued
- Twice, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 16, 2026 | Sep 16, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 16, 2026 | Sep 16, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 22, 2026 | Sep 22, 2026 | Not Applicable |
Zoning review Planning · CP-ZOC | Sep 28, 2026 | Sep 28, 2026 | Not Applicable |
Building plan review Building Inspection · BLDG | Oct 6, 2026 | Oct 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 8, 2026 | Oct 8, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 8, 2026 | Oct 8, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 8, 2026 | Oct 8, 2026 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Oct 15, 2026 | Oct 15, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 15, 2026 | Oct 15, 2026 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Oct 15, 2026 | Oct 15, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 28, 2026 | Oct 28, 2026 | Approved |
Plumbing inspector Building Inspection · PID-INSP | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Filed
- Estimated cost
- $100,000
| Name | Role | License on permit |
|---|---|---|
| Jeff Chow Ice Group Inc | Architect | C81252 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2017