2175 03rd St
San Francisco permit 202609188376 · Potrero Hill
#1c: renovation of an (e) shell space into a medical and cosmetic skin outpatient treatment facility. including: (n) interior walls, (n) dropped ceilings, (n) mep infraucture & construction of (n) specialized treatment rooms including injector, laser, aesthetician, and consultation spaces,
- Filed
- Sep 18, 2026
- Issued
- Oct 28, 2026 (1 month after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2026 were typically issued within 1 month (median of 3,682 issued permits).
- Review stops
- 19 stops across 5 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 18, 2026 | Sep 18, 2026 | Administrative |
Apartment and hotel inspection Building Inspection · HIS | Sep 18, 2026 | Sep 18, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 21, 2026 | Sep 21, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 21, 2026 | Sep 21, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 21, 2026 | Sep 21, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 21, 2026 | Sep 21, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 21, 2026 | Sep 21, 2026 | Approved |
Intake Building Inspection · INTAKE | Oct 20, 2026 | Oct 20, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Oct 20, 2026 | Oct 20, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 20, 2026 | Oct 20, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 21, 2026 | Oct 21, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 21, 2026 | Oct 21, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 21, 2026 | Oct 21, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 22, 2026 | Oct 22, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Oct 22, 2026 | Oct 22, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 22, 2026 | Oct 22, 2026 | Approved |
Address verification Building Inspection · ADDR | Oct 22, 2026 | Oct 22, 2026 | Administrative |
Public health review Public Health · HEALTH | Oct 23, 2026 | Oct 23, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 28, 2026 | Oct 28, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $500,000
| Name | Role | License on permit |
|---|---|---|
| Dane William Bunton Bunton Mousavi Architecture | Architect | C36022 |
| Steven Kirk Barg Steve Barg Structural Designs | Engineer | S5983 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025