3650 21st St
San Francisco permit 202610089187 · Castro/Upper Market
Construction of a new detached, 1 story, type v-b, residential adu in rear yard.
- Filed
- Oct 29, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 15 stops across 6 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 6, 2026 | Oct 26, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 2, 2026 | Nov 2, 2026 | Administrative |
Address verification Building Inspection · ADDR | Nov 2, 2026 | In progress | In Progress |
Zoning review Planning · CP-ZOC | Nov 2, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | Nov 2, 2026 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Nov 2, 2026 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 2, 2026 | In progress | — |
Fire prevention review Fire Department · SFFD | Nov 2, 2026 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Nov 2, 2026 | Nov 4, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Nov 2, 2026 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 2, 2026 | In progress | — |
Public Utilities programs review Public Utilities · SFPUC-PRG | Nov 2, 2026 | In progress | — |
Permit Processing Center Building Inspection · PPC | Nov 2, 2026 | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Filed
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Eric M Dumican Dumican Mosey Architects | Architect | C31398 |
| Daniel Polivka Holmes | Engineer | C79948 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2019