CheckMyDesigner

When do you need a building permit in San Francisco (and California)?

Last checked Nov 6, 2026

The short answer

  • Most work on a San Francisco house needs a building permit: building, altering, repairing, moving or demolishing.
  • Only a short list of small jobs is exempt. Check that list before you assume your job is on it.
  • Electrical, plumbing and mechanical work needs its own permit, even when the building work doesn’t.
  • Simple jobs can often get an over-the-counter permit. Bigger ones go through plan review with drawings.
  • Not sure? Ask DBI before you start, not after.

In San Francisco, you need a building permit before you construct, enlarge, alter, repair, move, demolish, or change the occupancy of any building, with only a narrow list of written exemptions in San Francisco Building Code (SFBC) Section 106A.1 and Section 106A.2. Even when a small structure or surface finish is exempt from a building permit, electrical, plumbing, or mechanical work usually still needs its own trade permit from the San Francisco Department of Building Inspection (DBI).

A building permit is official written authorization from your local building department confirming that your planned construction meets structural, fire, electrical, plumbing, and zoning codes (SFBC Section 106A.1). Once DBI issues the permit, city inspectors check the work in stages and sign off when the job is complete. That sign-off becomes part of your property’s permit record.

Which home projects need a permit in San Francisco

In San Francisco, the cutoff between permit-required work and exempt work is defined in SFBC Section 106A.2 and summarized on SF.gov’s construction permit guide. Use the table below to check common residential projects before you hire a crew.

Common San Francisco home projects and whether a building permit is required
ProjectPermit required in SF?San Francisco rule and threshold
Interior painting, wallpapering, and similar finish workNoExempt as surface finish work when no framing, drywall, plumbing, or wiring changes.
Flooring and carpet replacementNo, except in bathroomsFloor coverings are exempt in areas other than bathrooms.
Minor interior plaster or drywall patchNo (unless needed for fire protection)Minor repairs to existing interior plaster or wallboard are exempt unless they are required for fire protection.
Interior doorsNo (unless needed for fire protection)Replacing inside doors is exempt unless they are required for fire protection. Replacing garage doors is not on the exempt list; SF.gov lists it as an over-the-counter job without plans.
Window replacement or exterior doorsYes (glass-only repair is exempt)Replacing windows or doors in kind (same size and location) needs a permit, applied for through PermitSF without plans. Street-facing windows may also need to meet Planning’s window standards. Repairing or replacing glass is exempt.
Kitchen or bathroom remodel (even in-kind cabinet or fixture swap)YesIn-kind, non-structural work in a house or duplex (R-3), or in a unit of an apartment building built before 1991 (R-2), can apply online through PermitSF without plans. Other kitchen and bath work needs plans. Plumbing and electrical work need their own permits.
Moving, adding, or removing any wall (load-bearing or non-bearing)YesAltering interior partitions or structural framing requires a building permit and scaled floor plans.
Re-roofingYes, if more than 25% of the roof in 12 monthsReroofing is exempt only when no roof sheathing is installed, repaired or removed and the area reroofed in any 12-month period is no more than 25 percent of the roof. Anything more needs a permit. Non-structural reroofing can apply online through PermitSF without plans.
Decks, platforms, walks, and drivewaysDepends on height and locationExempt only if not part of an exit, no more than 30 inches above grade, and not over any basement or story below. Where the building must be accessible, it also can’t be part of a required accessible route.
Fences and retaining wallsDepends on height and locationFences up to 6 feet high at the rear and side lot lines at the rear of the property are exempt, and so is any fence up to 3 feet high. Taller fences elsewhere need a permit. Retaining walls up to 4 feet, measured from the bottom of the footing to the top of the wall, are exempt if they don’t support a surcharge.
One-story detached tool or storage shedNo, if the floor area is 120 sq ft or less (building permit only)One-story detached tool and storage sheds and playhouses are exempt if the floor area is 120 sq ft or less. Running power or water usually still requires trade permits.
ADU, garage conversion, seismic retrofit, or room additionYesRequires full building permit, architectural and structural plans, and trade permits.

Sources: SFBC 106A.2 · SF.gov exemptions · SF.gov plans guide · SF.gov exterior OTC guide · SF.gov remodel permit · SFBC Table 1A-G · SFBC 106A.1 · SF.gov soft story guide

An exemption in SFBC Section 106A.2 only waives the building permit. It does not authorize work that violates the Planning Code, historic district rules, or state energy and fire codes, and it does not cover electrical, plumbing, or mechanical permits.

Why San Francisco rules are stricter than the California baseline

Across California, the statewide baseline for one- and two-family homes is California Residential Code (CRC) Section R105.2. Cities and counties can amend the state code for local conditions, and San Francisco keeps its own exempt list in SFBC Section 106A.2.

If you read a national remodeling blog or even a general California checklist, several items listed as exempt statewide actually require a permit in San Francisco:

Skip the permit on a project that needs one and you risk a Stop Work Order and an investigation fee of nine times the permit issuance fee plus the original permit fee (SF.gov notice of violation, SFBC Section 110A, Table 1A-K). We cover those penalties in detail in what happens if you build without a permit in San Francisco.

Over-the-counter vs. in-house review at DBI

San Francisco divides building permit applications into two review tracks based on complexity (SF.gov building permit review processes).

Over-the-counter (OTC) review handles straightforward residential projects using Form 3/8 (SF.gov OTC permits). Simple no-plans jobs, such as in-kind window replacements, non-structural reroofing, and in-kind, non-structural kitchen or bath work in a house or duplex (R-3) or in a unit of an apartment building built before 1991 (R-2), must be submitted online through PermitSF (SF.gov check if your permit needs plans). OTC projects that require drawings are submitted in person at the Permit Center at 49 South Van Ness. SF.gov estimates 2 to 8 hours for that step (SF.gov interior remodel OTC guide).

In-house review applies when a project is too complex to review in a single counter visit, requires neighborhood notification under the Planning Code, adds a dwelling unit, or substantially expands the building envelope (SF.gov building permit review processes). You submit PDF drawings electronically for Bluebeam plan check, and staff across Planning, DBI building inspection, structural engineers, and the Fire Department review them in sequence.

When you need plans and who may draw them

DBI requires construction drawings whenever your project changes a floor plan, removes or relocates a wall, alters structural framing, converts a basement or garage, adds bedrooms or bathrooms, or modifies stairs, decks, or exterior walls (SF.gov check if your permit needs plans).

Under California B&P Code §5537 and B&P Code §6737.1, an unlicensed building designer or homeowner may prepare plans for single-family wood-frame houses and wood-frame buildings of up to four units that do not exceed two stories plus a basement, as long as the design stays within conventional wood-frame construction tables.

Whenever any portion of the work departs from conventional wood framing, such as removing a bearing wall for a long-span steel beam, cutting a wide garage opening, or underpinning a foundation, the local building official must require plans and calculations signed and stamped by a California-licensed architect or registered civil or structural engineer (B&P Code §5537(b), §6737.1(b)). San Francisco also mandates licensed design on steep hillside parcels in the Edgehill Mountain and Northwest Mt. Sutro Slope Protection Areas (SFBC Section 106A.3.2 Exception 2). Read our guides on architect vs. building designer in California and when you actually need an architect before choosing who draws your set.

How to check with DBI before you start

If your scope sits near a code boundary, verify before demolition starts rather than relying on a contractor’s verbal assurance:

  1. Confirm whether your scope needs a permit and whether it requires architectural drawings using DBI’s project permit guide and plans checklist.
  2. Check your property’s existing permit history and authorized unit count in the SF.gov Permit and Complaint Tracking System so you know whether past work was properly signed off.
  3. If your project needs plans, verify the California license status and San Francisco permit track record of your architect or structural engineer before signing a design contract.
  4. When in doubt about a borderline repair, ask DBI Technical Services or the Public Information Counter at 49 South Van Ness before starting work.

Common questions

What can you build without a permit in California?

Statewide, California Residential Code Section R105.2 exempts one-story detached sheds up to 120 square feet, fences up to 7 feet tall, retaining walls up to 4 feet from footing bottom to top, low decks under 30 inches above grade, and cosmetic work like painting. San Francisco’s own list in SFBC Section 106A.2 uses the same 120-square-foot limit for sheds but is narrower for fences: up to 6 feet only at the rear and side lot lines at the rear of the property, and up to 3 feet anywhere else. It does not exempt bathroom flooring or kitchen cabinets and countertops (SF.gov check if your project needs a permit).

Can a homeowner pull their own building permit in San Francisco?

Yes. DBI asks every OTC applicant to state their role on the project, and owners who apply fill out an owner package (SF.gov interior remodel OTC guide). Contractors fill out a separate contractor statement. Electrical and plumbing permits are usually pulled by the licensed trade contractors who do that work.

Do I need a permit to replace windows in San Francisco?

Yes. Replacing windows requires a building permit in San Francisco, even when the new windows are the same size and in the same location. In-kind replacements can apply online through PermitSF without plans (SF.gov check if your permit needs plans, SF.gov exterior residential OTC guide). Repairing or replacing glass is exempt under SFBC Section 106A.2. Street-facing windows may also need to meet San Francisco Planning Department material and profile rules.

How long does it take to get a building permit in San Francisco?

Simple no-plans permits are applied for online through PermitSF, and SF.gov does not publish a set processing time for them. For OTC permits with plans, SF.gov estimates 2 to 8 hours to submit in person at the Permit Center (SF.gov interior remodel OTC guide). Complex projects routed to in-house review can take months, depending on Planning notification and plan-check rounds. For an ADU on a lot that already has a house or apartment building, state law requires the city to approve or deny a complete application within 60 days (California Government Code §66317(a)(3)).

Hiring someone to draw your permit plans?

Before you sign a design contract, search any architect or engineer by name or license number to see their California license status, disciplinary history, and past San Francisco building permits.

For example “Jordan Lee”, C-34567 or S 5123.

Sources

  1. San Francisco Building Code Section 106A (Permits & Work Exempt from Permit), American Legal Publishing / City and County of San Francisco. Read Nov 6, 2026.
  2. San Francisco Building Code Section 110A, Table 1A-G & Table 1A-K (Fee Schedules), American Legal Publishing / City and County of San Francisco. Read Nov 6, 2026.
  3. Check if your construction project needs a permit, City and County of San Francisco (SF.gov). Read Nov 6, 2026.
  4. Check if your building permit needs plans, City and County of San Francisco (SF.gov). Read Nov 6, 2026.
  5. Learn about our building permit review processes, City and County of San Francisco (SF.gov). Read Nov 6, 2026.
  6. Get an OTC permit for your interior residential remodel, City and County of San Francisco (SF.gov). Read Nov 6, 2026.
  7. Apply for a kitchen or bath remodel permit, City and County of San Francisco (SF.gov). Read Nov 6, 2026.
  8. California Residential Code, Section R105.2 (Work Exempt from Permit), International Code Council / California Building Standards Commission. Read Nov 6, 2026.
  9. Notice of Violation (NOV), City and County of San Francisco (SF.gov). Read Nov 5, 2026.
  10. California Government Code §66317 (Accessory dwelling unit permit approvals), California Legislative Information. Read Nov 6, 2026.
  11. California Business and Professions Code §5537 & §6737.1 (Exemptions), California Legislative Information. Read Nov 5, 2026.

This is general information, not legal advice.