Douglas Wayne Mehl
Architect · Fennie + Mehl Architects · San Francisco
Public records
From the licensing board and the city of San Francisco.
The short answer
- Licensed?
- License activeArchitect C-17504First issued Sep 26, 1986, expires Feb 28, 2027.
Source: DCA license roster, retrieved Nov 5, 2026
- Any board discipline?
- None found.
We searched the California Architects Board enforcement list on Nov 5, 2026.
- Worked in San Francisco?
- 74 permits since 2005, 74 in the last 5 years. Latest filed Mar 12, 2026.
- What kind of projects?
- Commercial or tenant improvement 71 · Home remodel 1 · Legalize or fix a violation 1
- How long do their permits take?
- Commercial or tenant improvement: within 1 month. City typical for the same review: within 1 month.
Permits filed each year
San Francisco permits by the year they were filed. The last 5 years are in blue.
What are you planning?
Pick your kind of project to see their permits for it.
Commercial or tenant improvement: 71 permits in San Francisco
Time to get a permit
Median from filing to permit, from 68 issued permits filed since 1966; 1 still in review. City is the San Francisco median for the same kind of review, from 23,779 permits.
Where
- Financial District/South Beach50
- Mission8
- Mission Bay6
- South of Market4
Most recent
- 501 02nd StSte 501. (2) new privacy pods. provide seismic anchorage to concrete slab.Mar 12, 2026Complete
- 501 02nd St#150: installing 3 new privacy pods. provide seismic anchorage to concrete slab.Dec 3, 2025Complete
- 1 California St8th floor; interior demolition of ceiling height partitions construction of new partiations, doors, glazing, millowrk, finishes, associated mechanical, electrical, and plumbing.Dec 26, 2024Complete
- 501 02nd St6th fl/ ste 615. t.i. n) partitions, millwork, glazing, finishes, power/lighting/mech distribution. all non-structural.May 20, 2024Complete
- 350 Brannan St2/f -demolition existing ceiling height partition, construction of new full height partitions, doors, millwork and finishes. associated power/lighting distribution, associated mechanical system distribution, associated life safety system changes and plumbing. structural scope of work encompassesMay 7, 2024Complete
| Filed | Project | Type | Status | Time to permit | Open |
|---|---|---|---|---|---|
| Mar 20, 2026 | 501 02nd St 1st/f ste# 150: revision to 202512030848, install 2 phone pods Complete | Revision or supplement | Complete | Within 1 month | |
| Mar 12, 2026 | 501 02nd St Ste 501. (2) new privacy pods. provide seismic anchorage to concrete slab. Complete | Commercial or tenant improvementType unconfirmed | Complete | Within 1 month | |
| Dec 3, 2025 | 501 02nd St #150: installing 3 new privacy pods. provide seismic anchorage to concrete slab. Complete | Commercial or tenant improvement | Complete | Within 1 month | |
| Aug 19, 2025 | 501 02nd St 1st/f ste# 150: provide seismic anchorage to privacy pods per fire department nov 2506-0190 dated 6/11/25 Complete | Legalize or fix a violation | Complete | Within 1 month | |
| Dec 26, 2024 | 1 California St 8th floor; interior demolition of ceiling height partitions construction of new partiations, doors, glazing, millowrk, finishes, associated mechanical, electrical, and plumbing. Complete | Commercial or tenant improvement | Complete | Within 1 month | |
| May 20, 2024 | 501 02nd St 6th fl/ ste 615. t.i. n) partitions, millwork, glazing, finishes, power/lighting/mech distribution. all non-structural. Complete | Commercial or tenant improvement | Complete | Within 1 month | |
| May 7, 2024 | 350 Brannan St 2/f -demolition existing ceiling height partition, construction of new full height partitions, doors, millwork and finishes. associated power/lighting distribution, associated mechanical system distribution, associated life safety system changes and plumbing. structural scope of work encompasses Complete | Commercial or tenant improvement | Complete | 23 months | |
| May 6, 2024 | 350 Brannan St Barrier removal only -demo ofpartitions, entry landing, g/f entry lobby & stair improvement & finishes, structural scope encompasses concrete infill & concrete stair at vestibule, stair stringer & glass guardrail attachment. associated ele/power/lighting distribution. Filed | Commercial or tenant improvement | Filed | — | |
| Dec 13, 2023 | 350 Brannan St Decommission and demolition of (e) freight elevator. infill pit with new grade floor slab. establish and document wholesale sales use on the ground floor pursuant to the sf planning code. Issued | Commercial or tenant improvement | Issued | 5 months | |
| Nov 16, 2023 | 501 02nd St 6th floor (ste# 615): ti demo millwork; lighting (n) full-weight partitions, millwork, mep. Complete | Commercial or tenant improvement | Complete | Within 1 month | |
| Nov 16, 2023 | 501 02nd St Ste 600: t.i. demo full height partitions, construct new partitions, doors, millwork, mep. demising new ste 600, ste 615 and base buidling corridor. Complete | Commercial or tenant improvement | Complete | Within 1 month | |
| Aug 16, 2023 | 350 Brannan St Demo: remove all non-structure interior walls and ceiling on the 2nd floor Issued | Commercial or tenant improvement | Issued | Within 1 month | |
| May 25, 2023 | 350 Brannan St Establish office use per 2021-011143zad zoning administrator determination letter. renovate ground and 2nd floors. no work on 3rd floor. demolition of existing ceiling height partitions, new full height non bearing partition walls, cold form steel infill and glass guardrail attachments, mep deferred Withdrawn | Commercial or tenant improvementType unconfirmed | Withdrawn | — | |
| Jan 6, 2023 | 501 02nd St Demising (e) suite 120 into 2 separate suites. (e) suite 120 no new construction. (n) suite 150: const new full height partitions, doors, glazing, millwork, finishing and asscos power ltg distribution. deferred life safety, elec & mech Complete | Commercial or tenant improvement | Complete | Within 1 month | |
| Dec 27, 2022 | 501 02nd St 7/f suite 710: demolition of some existing non bearing ceiling height walls, construction of new full height partitions, glazing, pantry, millwork, plumbing, finishes and assoc. electrical power/light dist. deferred: life safety, elect, mech and plumbing. Complete | Commercial or tenant improvement | Complete | Within 1 month | |
| Dec 6, 2022 | 501 02nd St Suite 650: new millwork base/upper cabinets, new sink, associated electrical power/lighting distribution & associated plumbing Complete | Commercial or tenant improvement | Complete | Within 1 month | |
| Nov 10, 2022 | 201 Mission St Fl 2,3,16: minor casework and accessibility upgrade: interior work only. existing hvac system to remain. Complete | Commercial or tenant improvement | Complete | Within 1 month | |
| Jun 21, 2022 | 4 Embarcadero Center 26th flr ste 2600: interior demolition, new full/partial height partitions, ceiling and millwork. mep & life safety under separate permits. restroom upgrades. Complete | Commercial or tenant improvement | Complete | 1 month | |
| May 24, 2022 | 1 Bush St #0 13th floor- revision to approved arch permit. m.e.p revision submittal included in set. ref: 202202047388. Complete | Revision or supplement | Complete | Within 1 month | |
| May 12, 2022 | 501 02nd St Ste 500: creating of huddle room. mep & sprinklers deferred. Complete | Commercial or tenant improvement | Complete | Within 1 month |
Sources: DataSF i98e-djp9, 3pee-9qhc, retrieved Nov 5, 2026. Names on permits are matched to licenses by license number and name; unmatched records are not shown.