Dennis C Budd
Architect · Dennis Budd Aia Architect · San Francisco
Public records
From the licensing board and the city of San Francisco.
The short answer
- Licensed?
- License activeArchitect C-26969First issued Jun 23, 1997, expires Dec 31, 2027.
Source: DCA license roster, retrieved Nov 5, 2026
- Any board discipline?
- None found.
We searched the California Architects Board enforcement list on Nov 5, 2026.
- Worked in San Francisco?
- 24 permits since 2005, 24 in the last 5 years. Latest filed Jun 30, 2026.
- What kind of projects?
- Home remodel 10 · Addition 6 · Deck, stairs or patio cover 2
- How long do their permits take?
- Home remodel: 2 months. City typical for the same review: within 1 month.
Permits filed each year
San Francisco permits by the year they were filed. The last 5 years are in blue.
What are you planning?
Pick your kind of project to see their permits for it.
Home remodel: 10 permits in San Francisco
Time to get a permit
Median from filing to permit, from 9 issued permits filed since 1966; 1 still in review. City is the San Francisco median for the same kind of review, from 19,947 permits.
Where
- Pacific Heights3
- Outer Richmond1
- Castro/Upper Market1
- Marina1
Most recent
- 5600 Fulton St1.convert 237 sqft uncond. to habitable space @1st flr main unit. 2. remodel guest suite @1st flr main unit, 3. remove main unit int. service stair & expand /remodel kitchen 4.relocate kitchenette, add main bedroom, bath & closet @ 2nd unit, 5.remove serv entry door & provide selective window work @Jun 30, 2026Issued
- 282 Eureka StKitchen renovation w/ (n) fixtures, finishes, cabinets, & appliances, modify interior openings @ kitchen, breakfast, entry, & family rooms @ 2nd fl. convert (e) closets @ 3rd fl to (n) main bath w/ (n) skylight. install (n) exterior doors & windows within (e) openings all flrs. repair/replace (e)...Jun 25, 2026Issued
- 25 Retiro WyReplace fixtures & finishes in kind in existing locations for 3 baths & 1 kitchen. replace hardwood flooring with new hall shower will be enlarged.Apr 30, 2026Issued
- 535 Oak Park Dr(n) 9 sq ft front facade bay window. replace stucco at front and side facade w/ (n) siding. interior renovation at 2/f. kitchen, bedrooms, and bathrooms. (n) finishes on (e) ext stair structure. (n) 2/f windows and skylights. (n) lighting and mech supply ducting at 2/f. (e) gas furnace to remain.Apr 1, 2026Issued
- 2566 Pine StDemo and rebuild (e) entry stair from 1st to 2nd fl (interior stair). reframe (e) wall between common vestibule and unit 1 foyer to accomodate (n) pocket doors mis. elec per plansFeb 27, 2026Issued
| Filed | Project | Type | Status | Time to permit | Open |
|---|---|---|---|---|---|
| Jun 30, 2026 | 5600 Fulton St 1.convert 237 sqft uncond. to habitable space @1st flr main unit. 2. remodel guest suite @1st flr main unit, 3. remove main unit int. service stair & expand /remodel kitchen 4.relocate kitchenette, add main bedroom, bath & closet @ 2nd unit, 5.remove serv entry door & provide selective window work @ Issued | Home remodel | Issued | 1 month | |
| Jun 25, 2026 | 282 Eureka St Kitchen renovation w/ (n) fixtures, finishes, cabinets, & appliances, modify interior openings @ kitchen, breakfast, entry, & family rooms @ 2nd fl. convert (e) closets @ 3rd fl to (n) main bath w/ (n) skylight. install (n) exterior doors & windows within (e) openings all flrs. repair/replace (e)... Issued | Home remodel | Issued | 2 months | |
| Jun 11, 2026 | 889 Elizabeth St Replace (e) solar tube sky light in flat glass model. add 1-hr fire rated roof parapet. replace (e) kitchen cabinet in kind. no plumbing shifts. Issued | OtherType unconfirmed | Issued | Within 1 month | |
| Apr 30, 2026 | 25 Retiro Wy Replace fixtures & finishes in kind in existing locations for 3 baths & 1 kitchen. replace hardwood flooring with new hall shower will be enlarged. Issued | Home remodel | Issued | Within 1 month | |
| Apr 1, 2026 | 535 Oak Park Dr (n) 9 sq ft front facade bay window. replace stucco at front and side facade w/ (n) siding. interior renovation at 2/f. kitchen, bedrooms, and bathrooms. (n) finishes on (e) ext stair structure. (n) 2/f windows and skylights. (n) lighting and mech supply ducting at 2/f. (e) gas furnace to remain. Issued | Home remodelType unconfirmed | Issued | 3 months | |
| Mar 5, 2026 | 3555 Mission St Corrective action to address nov 202649136. rebuild existing wood deck to comply. Issued | Legalize or fix a violation | Issued | Within 1 month | |
| Feb 27, 2026 | 2566 Pine St Demo and rebuild (e) entry stair from 1st to 2nd fl (interior stair). reframe (e) wall between common vestibule and unit 1 foyer to accomodate (n) pocket doors mis. elec per plans Issued | Home remodelType unconfirmed | Issued | Within 1 month | |
| Feb 4, 2026 | 72 Harper St Revision to to pa 202303163798 documentation of existing and proposed gable roof slope tp 10:12 slope (correction from 9:12 roof slope); proposed bldg height increased from 30'-4 1/2" (approved) to 31'-7 1/2" above grade. note: no change to proposed demo, proposed scope of work, or project valuation Issued | Revision or supplement | Issued | Within 1 month | |
| Nov 20, 2025 | 897 Clayton St Excavation (n)foundations, lower 1/f to increase ceiling height from 7'-0" to 9'-6". (n) 1/f partitioning incld family room, gym, bath, storage, mech room & inter stairs. convert 2/f rear window to door for (n)spiral stair access to yard. (n)fire wall @ north prop line. (n) rear yard retaining wall Filed | Home remodelType unconfirmed | Filed | — | |
| Oct 29, 2025 | 72 Harper St Revised permit to pa 202303163798 revision and/or removal of door and windows. infill 10 sf at the 3rd floor. Issued | Revision or supplement | Issued | Within 1 month | |
| Jul 30, 2025 | 286 Eureka St Upgrade (e) front windows to (n) windows within (e) rough opening w/lower sill; (n) window @ rear Reinstated | Other | Reinstated | Within 1 month | |
| Jun 4, 2025 | 5 Montague Pl New roof deck. int & ext stairs for roof deck access. new skylights, fire rated. parapets & roof stair / deck guards. expand garge to include storage / mech rooms. new garage conc floor slab, foundation upgrades. new garage door & rear facade sliding doors. lower (e) rear patio on grade. relocate / Triage | Deck, stairs or patio coverType unconfirmed | Triage | — | |
| Apr 29, 2025 | 1462 11th Av Revision to 202311201167: structural work increase at 1st fl foundation (north & east exterior walls) & area of interior concrete slab on grade replacement Issued | Revision or supplement | Issued | Within 1 month | |
| Mar 6, 2025 | 2448 Folsom St 2/f interior remodel to relocate main bath and add new hall bath. open 144 sq ft of unfinished attic to hall below, provide new insulation. (2) new skylights. mechanical, electrical, and plumbing rerouting and upgrading in area of work. replace 4 windows 1 facing st. u>.30 Complete | Home remodel | Complete | 2 months | |
| Nov 7, 2024 | 701 Buena Vista West Av Alter site to pa 202207138359 - fill in 47sf building notch on 2/f for kitchen use. Issued | Revision or supplementType unconfirmed | Issued | 3 months | |
| Oct 3, 2024 | 2671 17th Av Revision to pa # 2022-0304-9310 remove from rear deck scope: demo (e) 2-story rear wood deck & stairs, replace with (n) steel framed decks with spiral stair. minor interior partition changes and changes to (n) exterior window sizes Complete | Revision or supplement | Complete | Within 1 month | |
| Jul 31, 2024 | 2255 Clay St Interior renovation of 3/f kitchen, laundry and eating spaces. 4/f: to create a new guest bedroom and remodel (e) office area. drop 195 sq.ft of built-up floor framing at 4/f to match height of (e) adj. office area. mep work throughout 4/f interior spaces. Complete | Home remodel | Complete | 2 months | |
| May 4, 2023 | 1455 12th Av 3-story rear horizontal addition. excavate lower 1st floor slab on grade. convert partial garage to living space. (n) interior 1st to 2nd flr stair. (n) green & solar ready roofs. (n) fixtures & finishes. expand hydronic radiant heating. relocate utility meters. repave downsloping driveway. Approved | Addition | Approved | — | |
| Mar 29, 2023 | 559 Liberty St Replace e rear yard facde french doors & double hung windows w/ new door system, replace e wood trellis w/ steel-wood hybrid type, design in-knd, replace e rear yard elec outlets/lighting, hose bibs &irrigation systems, relocate e rear yard masonry steps, ret.walls & patio w/new cip concrete. Complete | Deck, stairs or patio coverType unconfirmed | Complete | 8 months | |
| Mar 16, 2023 | 72 Harper St 3 story rear addition,convert 1st fl to adu,elevate portion of roof,interior partition changes on all fls,construct excavated rear yard light court,re-build front steps in kind to met egress code,install fire sprinkler stystem,full seismic upgrade of bldg,new fixtures fitting & finishes throughout. Issued | ADU | Issued | 15 months |
Sources: DataSF i98e-djp9, 3pee-9qhc, retrieved Nov 5, 2026. Names on permits are matched to licenses by license number and name; unmatched records are not shown.